Gresford 1 Water Pump Station Upgrade

Client Organisation: Hunter Water Corporation
Date completed: February 2011
Project Duration: 5 months
Project Value: $400k

The project involved the construction of a new water inlet gravel screened structure in the Patterson River which delivered water to a wet well arrangement in the riverbank. A new Polypropylene watermain was laid and connected into the existing water main to the high-level water reservoir.