HEZ WWPS – Kurri Kurri

Client Organisation: Keller Civil Engineers (KCE)
Date completed: 2011
Project Duration: 11 months
Project Value: $1.6m

The project involved the construction of a new DN 600 ductile iron gravity main up to 7 meters in depth to a new wet well pumping station. All structures were required to be constructed on a 600mm x 600mm concrete beam to protect against settlement due to isolated mine subsidence occurrences.

HEZ WWPS Kurri Kurri
HEZ WWPS Kurri Kurri
HEZ WWPS Kurri Kurri
HEZ WWPS Kurri Kurri