Namoi Village (Walgett) precast Waste-Water Pump Station

Client Organisation: Department of Commerce
(Milbant Constructions P/L)
Date completed: August 2014
Project Duration: 5 months
Project Value: $509k

Rivers Constructions was engaged to construct a new wet well pumping station for the indigenous community at Namoi Village, north of Walgett.

Due to the remoteness of the site Rivers Constructions constructed the station at its West Gosford facility, fully assembled it then disassembled and transported to the site for installation. A great example of Rivers Constructions innovative approach to construction and their ability to plan in detail.

The project included Level 1 electrical works, switchboard manufacture and installation.

Namoi Village precast Waste Water Pump Station
Namoi Village precast Waste Water Pump Station
Namoi Village precast Waste Water Pump Station
Namoi Village precast Waste Water Pump Station
Namoi Village precast Waste Water Pump Station
Namoi Village precast Waste Water Pump Station
Namoi Village precast Waste Water Pump Station
Walgett Namoi Village WWPS3
Walgett Namoi Village WWPS3