Client Organisation: | Central Coast Council |
Date completed: | May 2018 |
Project Duration: | 2 months |
Project Value: | $80k |
The project involved the design and construction of the new recirculation pipe work and interconnecting lines between the inlet works, sludge pump station and the back-wash pumps.