Army Pump Station Refurbishment

Client Organisation: Singleton Council
Date completed: January 2019
Project Duration: 2 months
Project Value: $170k

The refurbishment of a wet well / dry well arrangement which had been in service for over 30 years.

Rivers Constructions were engaged to design and replace the existing 3 pump arrangement with a two-pump arrangement along with a new bypass point.

The project also included the bypassing of the station whilst the works were being undertaken.

Rivers Constructions completed the project on time and budget without incident.