CPA/2291 Toukley SPS TO01, 06 & 09 Refurbishments
Client Organisation: Central Coast Council Date completed: March 2022 Project Duration: 21 months Project Value: $7.2m
Client Organisation: Central Coast Council Date completed: March 2022 Project Duration: 21 months Project Value: $7.2m
Refurbishment of a wet well / dry well arrangement which had been in service for over 30 years in Singleton.
Rivers Constructions designs and constructions new waster-water pumping station
Construction of new wet well pumping station Namoi Village using remote construction technology and transporting to site and installed along with electrical works and switchboard
Construction of a new gravity main up to 7 meters deep to a new wet well pumping station with structures constructed on a concrete beam to prevent subsidence
Construction of a new water inlet gravel screened structure in the Patterson River which delivered water to a wet well arrangement in the riverbank plus new polypropylene watermain.